To start a new perfume project, normally there tends to be three options on glass bottles, including standard perfume bottle, glass bottle in stock and custom perfume bottle design. Different choices take diverse production time, so when you are making plans, better to take this into consideration carefully. As the professional wholesale perfume bottles manufacturer, we would like to share with you some useful information as below.

Standard Bottle: takes 2 months of preparation (first of all, select the bottle you prefer)

5-7 days: finalize decoration designs on bottles, including which color to be coated, printing design and etc. (if you design artwork is ready, then this step is not required)

7-15 days: prepare samples with your personalized decorations; ( if just plain bottle, then this step is not required)

5-7 days: send the pre-production samples for your final inspection;

60-65 days: plain bottle mass production, normally the quantity is inversely proportional to the production cycle, the bigger quantity, the shorter time;

15-20 days: decoration process ( if just plan bottle, then this step is not required)

Stock Bottle: takes 5-7 days

Plain bottle is ready, if make it with decorations then takes extra 15-20 days as above .

Custom Design: launching of a new project requires at least 5 months of preparation.

10-20 days: finalize the bottle design. To confirm the design soon, timely and full discussion between both parties is required and vital.

40-45 days: finish new glass mould, test mould and produce physical plain glass samples;

7-15 days: prepare samples with decorations, like color coating, logo printing/stamping;

5-7 days: send the pre-production samples for your final inspection;

60-65 days: plain bottle mass production, normally the quantity is bigger, the plain glass production time will be faster;

15-20 days: decoration.

Conclusion:

Process Stock Bottle Standard Bottle Customized Bottle
Finalizing New Design NO need NO need Needed
Finished Mold Time NO need NO need 35-40 days
Sampling time 7-15 days 7-15 days 7-15 days
MOQ 10,000pcs 20,000pcs 30,000pcs
Delivery Time 5-7days 60-65days 90-95days

Planning to make your own perfume brand?Come here Now! Our experienced sales team are open to discuss with you on design finalization and leadtime plan. You will get satisfactory answer about how to custom luxury perfume bottles in cost-effective way.